Charging and Depot Supply Chain

Chargers · power modules · transformers · switchgear

A fast charger cabinet ships off the shelf. The transformer feeding a truck depot took an average of 128 weeks to arrive in 2025, and the US imported about 80% of them.

Lead times for the equipment behind a charging depot in the US, Q2 2025: distribution transformers about 30 weeks, switchgear 44 weeks, power transformers 128 weeks, generator step-up transformers 144 weeks. The charger cabinet is the shortest item. US LEAD TIMES BEHIND A CHARGING DEPOT, Q2 2025 Charger cabinet shortest item Distribution transformer ~30 weeks Switchgear 44 weeks Power transformer 128 weeks Generator step-up 144 weeks 1 YR 2 YR Imports supply about 80% of US power transformers and 50% of distribution transformers.
Power transformer
128 weeks
Switchgear
44 weeks
Distribution
~30 weeks
Imported
~80% power
US shortfall
30%
Hub
Supply Chain

Lead times

The Charger Is the Fastest Part of a Depot to Get

Charger cabinets come off the shelf from ABB, Tesla, Kempower, Alpitronic and BTC Power. The medium-voltage service behind them waits on transformers and switchgear.

US lead times for grid equipment, Q2 2025
EquipmentLead timeImported shareWhere it sits in a depot
Distribution transformer~30 weeks; three-phase pad-mount longer~50%Steps utility voltage down for the chargers
Switchgear44 weeks-Protects and switches the depot's feed
Power transformer128 weeks~80%Substation feeding a multi-megawatt truck depot
Generator step-up transformer144 weeks-Connects on-site generation to the grid

Power transformer prices rose about 77% from 2019, and Wood Mackenzie put the 2025 US supply shortfall at 30% for power transformers and 10% for distribution transformers. Grain-oriented electrical steel (GOES), made by about six companies worldwide, is the input behind both. See the Electrification Bottleneck Atlas.

The depot

A Truck Depot Is a Small Substation

Ten trucks on megawatt chargers draw about 10 MW, as much as several thousand homes at peak. That turns a fleet depot into a utility project with its own transformer, switchgear and often a battery buffer.

Depots such as Tesla's Semi Megacharger sites, Greenlane's I-15 corridor site in Colton, California and WattEV's California depots are sized around the utility feed; on-site batteries cut peak demand while upgrades catch up. See Fleet Energy Depots and From Charging Depots to Fleet Energy Depots.

Charger hardware

Charger Makers Are Spread Out; Their Power Modules Are Not

DC fast charger supply
LayerLeading companiesNotes
Charger cabinetsABB E-mobility, Tesla, Kempower, Alpitronic, BTC Power, Tritium (Exicom), ChargePointAssembled in the US and Europe for Buy America and NEVI rules
Power modulesInfypower, UUGreen, Tonhe, plus in-house designsChinese module makers supply many charger brands
SiC devicesWolfspeed, Infineon, onsemi, STMicroSame wafers as EV inverters
ConnectorsNACS (SAE J3400), CCS, MCS (SAE J3271)NACS became the North American default from 2025

Sources

Sources and scope

Datasets
Charging equipment makers, charging networks, fleet depots
Lead times
US average quoted lead times by equipment type, Q2 2025
Sources
Wood Mackenzie supply chain lead-time benchmarking and transformer outlook (2025)