Facility Electrification

interconnection · substations · on-site energy

Large facilities now draw tens to hundreds of megawatts. The transformer and the interconnection study set the opening date.

Typical site loads: a hospital or campus 5 to 20 MW, a port terminal 20 to 60 MW, a large semiconductor fab 100 to 300 MW or more, and an AI data center campus 300 MW to over 1 GW, against ERCOT's 75 MW large-load review threshold. Schedules are set by interconnection, transformers at about 128 weeks in 2025 and switchgear at about 44 weeks. TYPICAL SITE LOAD Hospital or campus 5-20 MW Port terminal 20-60 MW Large fab 100-300+ MW AI data center campus 300 MW-1 GW+ ERCOT large-load review, 75 MW WHAT SETS THE SCHEDULE Interconnection Studies, upgrades Transformers ~128 weeks (2025) Switchgear ~44 weeks
Transformer wait
~128 wk
Switchgear
~44 wk
ERCOT review
75 MW
AI campus
1 GW+
Hub
Industry

Finding

For a large facility, the grid connection is the critical path, and the building comes second

AI data centers, fabs, ports and logistics campuses now draw tens to hundreds of megawatts each. At that size the schedule is set by the utility interconnection study, the substation transformer (about 128 weeks to deliver in 2025) and the switchgear lineup (about 44 weeks), not by construction.

Facilities respond in three ways. They order long-lead equipment during conceptual design, before the building is permitted. They phase energization, opening on a partial feed and growing into the full one. And they add on-site energy - batteries, solar, gas turbines or reciprocating engines - so part of the load can run before or without the grid. Texas shows all three: ERCOT reviews any new load of 75 MW or more, and its queue is dominated by data centers and industrial sites such as the Samsung Taylor fab and the campuses on AustinIO's Texas AI data center exemplars page.

Inside the fence, a facility now runs as an energy system: microgrid controllers dispatch batteries and generators, island the site during grid events and bid flexible load into utility programs. Fleets make it denser still, because electric yard tractors, forklifts and trucks charge on the same service.

Facility types

Where facilities are electrifying

Facility types
FacilityWhat electrifiesCoverage
Seaports and container terminalsCranes, yard tractors, shore powerSeaport Electrification
AirportsGround support equipment at flight banksAirport Electrification
Logistics hubs and fulfillment campusesDelivery and yard fleetsLogistics hubs
Rail hubs and intermodal yardsYard equipment and drayageRail hubs
MinesRemote sites; electric haul trucksIndustrial sites
Fabs and data centersProcess tools, cooling, IT loadProcess Electrification
FactoriesProcesses plus internal logisticsIndustrial sites

Power stack

From the utility to the load

Facility power stack
LayerWhat it doesNotes
Utility interconnectionFeeder capacity, protection coordinationStudies and upgrades; phased energization
MV/HV transformersStep utility voltage down to site distributionOrder early; dual-source; modular bays
Switchgear and buswaysProtect, switch and distribute powerArc-flash and coordination studies
On-site energyBESS, solar, CHP, gensets, turbinesPeak shaving, backup, bridge power
ControlsMicrogrid controller, EMS/SCADA, BMSIslanding, demand response, power quality

Sources

Sources and scope

Scope
Electrical infrastructure for large facilities: interconnection, substations, on-site energy and controls
Sources
Wood Mackenzie lead-time benchmarking (2025); ERCOT large-load rules; AustinIO
Updated
October 2026