Finding
For a large facility, the grid connection is the critical path, and the building comes second
AI data centers, fabs, ports and logistics campuses now draw tens to hundreds of megawatts each. At that size the schedule is set by the utility interconnection study, the substation transformer (about 128 weeks to deliver in 2025) and the switchgear lineup (about 44 weeks), not by construction.
Facilities respond in three ways. They order long-lead equipment during conceptual design, before the building is permitted. They phase energization, opening on a partial feed and growing into the full one. And they add on-site energy - batteries, solar, gas turbines or reciprocating engines - so part of the load can run before or without the grid. Texas shows all three: ERCOT reviews any new load of 75 MW or more, and its queue is dominated by data centers and industrial sites such as the Samsung Taylor fab and the campuses on AustinIO's Texas AI data center exemplars page.
Inside the fence, a facility now runs as an energy system: microgrid controllers dispatch batteries and generators, island the site during grid events and bid flexible load into utility programs. Fleets make it denser still, because electric yard tractors, forklifts and trucks charge on the same service.
Facility types
Where facilities are electrifying
| Facility | What electrifies | Coverage |
|---|---|---|
| Seaports and container terminals | Cranes, yard tractors, shore power | Seaport Electrification |
| Airports | Ground support equipment at flight banks | Airport Electrification |
| Logistics hubs and fulfillment campuses | Delivery and yard fleets | Logistics hubs |
| Rail hubs and intermodal yards | Yard equipment and drayage | Rail hubs |
| Mines | Remote sites; electric haul trucks | Industrial sites |
| Fabs and data centers | Process tools, cooling, IT load | Process Electrification |
| Factories | Processes plus internal logistics | Industrial sites |
Power stack
From the utility to the load
| Layer | What it does | Notes |
|---|---|---|
| Utility interconnection | Feeder capacity, protection coordination | Studies and upgrades; phased energization |
| MV/HV transformers | Step utility voltage down to site distribution | Order early; dual-source; modular bays |
| Switchgear and busways | Protect, switch and distribute power | Arc-flash and coordination studies |
| On-site energy | BESS, solar, CHP, gensets, turbines | Peak shaving, backup, bridge power |
| Controls | Microgrid controller, EMS/SCADA, BMS | Islanding, demand response, power quality |
Sources
Sources and scope
- Scope
- Electrical infrastructure for large facilities: interconnection, substations, on-site energy and controls
- Sources
- Wood Mackenzie lead-time benchmarking (2025); ERCOT large-load rules; AustinIO
- Updated
- October 2026