Microgrid Bottlenecks

transformers · turbines · switchgear · cells

A microgrid can be built in 6-18 months. Its transformer can take more than two years to arrive.

US build time against lead times, in months: a microgrid build takes 6 to 18 months; a large power transformer about 128 weeks (about 30 months); a generator step-up transformer about 144 weeks (about 33 months); and utility interconnection a median 61 months for projects built in 2025. BUILD TIME AGAINST LEAD TIMES, MONTHS (US) Microgrid build 6-18 months Large power transformer ~128 weeks Step-up transformer (GSU) ~144 weeks Utility interconnection 61 months Interconnection: median for projects built in 2025.
Large transformer lead time
~128 weeks
Step-up transformer
~144 weeks
US GOES producers
1
US transformer shortfall, 2025
30%
Hub
Energy

Finding

Microgrid schedules are set by a few long-lead items, led by transformers built on grain-oriented electrical steel from about 10 mills worldwide

Wood Mackenzie puts large power transformer lead times at about 128 weeks and generator step-up units at 144, with a US power transformer shortfall of 30% in 2025 that it expects to fall to about 5% by 2030 as new plants open from 2027. The cores need grain-oriented electrical steel (GOES); Cleveland-Cliffs' Butler Works in Pennsylvania is the only US producer.

Two older worries have eased. Silicon carbide is no longer scarce: Chinese substrate makers SICC and TanKeBlue expanded fast, prices fell, and Wolfspeed went through Chapter 11 restructuring in 2025; MW-scale battery and solar inverters mostly use silicon IGBTs anyway. LFP cells are in global oversupply, but US projects face tariffs and foreign-entity rules on Chinese cells, which push buyers toward LG Energy Solution, Samsung SDI, AESC and Tesla's US lines.

Gas turbines have become the new constraint for behind-the-meter microgrids at data centers: GE Vernova, Siemens Energy and Mitsubishi Power have sold slots years ahead, so developers turn to reciprocating engines (Caterpillar, Wärtsilä, INNIO Jenbacher), Bloom fuel cells and larger batteries. Factory-built blocks such as Tesla Megablock bundle the transformer and switchgear to take them off the critical path.

Ranked

Bottlenecks ranked

Microgrid bottlenecks
BottleneckConstraintStatus, late 2026Mitigation
Power transformersGOES supply; few US plants; US imports about 80% of large units~128-144 weeks for large unitsOrder early; standard designs; bundled blocks; amorphous-core distribution units
Gas turbinesData center demand filled order booksSlots sold years aheadEngines, fuel cells, batteries; used and refurbished units
MV switchgearLong lead for smart and SF6-free units; few vendorsTightStandard designs, dual sourcing
Battery cells (US)Tariffs and foreign-entity rules on Chinese LFPGlobal oversupply; US supply tightKorean and US-made LFP; domestic content planning
Interconnection approvalUtility studies, even for export-limited sitesYears for large loadsNon-export designs; flexible interconnection
Skilled laborLineworkers, relay technicians, commissioning engineersShortPrefabricated skids, factory testing
SiC power devicesFormerly shared with EVs and AIEased; oversupplyNone needed

GOES

Grain-oriented electrical steel mills

Transformer cores depend on these mills; China and Japan hold the most capacity.

GOES producers
CompanyMillCountry
Cleveland-CliffsButler Works, PennsylvaniaUS
Baowu SteelBaoshan, ShanghaiChina
Wuhan Iron and Steel (Baowu)Wuhan, HubeiChina
Nippon SteelHikari and YawataJapan
JFE SteelChiba and FukuyamaJapan
POSCOPohangSouth Korea
thyssenkrupp Electrical SteelGelsenkirchenGermany
voestalpineLinzAustria
Tata SteelIJmuidenNetherlands

SSTs

Solid-state transformers: relief, not a replacement

Solid-state transformers (SSTs) convert voltage with high-frequency silicon carbide switching at tens of kHz instead of a 50/60 Hz steel core, so they need far less GOES and are much smaller. They also add power conditioning and native DC output, which suits batteries, EV chargers and 800 V DC data center racks. Most units are low- and medium-voltage; costs per kVA are higher than iron-core units, and field reliability is still being proven. Heron Power, Amperesand and DG Matrix lead a startup wave; see Solid-State Transformers. Expect SSTs at depots, storage sites and data centers first, not at utility substations.

Sources

Sources and scope

Scope
Microgrid Deployment Bottlenecks
Sources
Wood Mackenzie transformer outlook (2025); LBNL interconnection data; ElectronsX GOES dataset
Updated
October 2026