Grid and Upgrades

transformers · switchgear · electrical steel

Power transformers take about 128 weeks to deliver and 80% of US supply is imported. The grid's binding constraint is a factory shortage, not a wire shortage.

US lead times in the second quarter of 2025: generator step-up transformers 144 weeks, power transformers 128 weeks, switchgear 44 weeks, distribution transformers 30 weeks. Imports supplied about 80% of US power transformers and 50% of distribution transformers. Power transformer demand rose 116% from 2019 and unit prices about 77%. US LEAD TIMES, Q2 2025 Step-up (GSU) 144 wk Power transformer 128 wk Switchgear 44 wk Distribution 30 wk 52 weeks = 1 year SHARE OF US SUPPLY IMPORTED, 2025 Power 80% imported Distribution 50% imported SINCE 2019 (POWER TRANSFORMERS) +116%demand +77%unit price 30%2025 shortfall
Power transformer lead
128 wk
Imported
80%
2025 shortfall
30%
US GOES makers
1
Hub
Energy

Finding

The grid is short of transformers, and the US imports 80% of the big ones

US demand for power transformers has risen 116% since 2019 and supply has not kept up: Wood Mackenzie put the 2025 shortfall at 30% for power transformers and 10% for distribution units. Large power transformers average 128 weeks to deliver and generator step-up units 144.

Imports fill the gap - about 80% of US power transformer supply and half of distribution supply - which puts tariffs straight into project costs. Unit prices are up about 77% for power transformers since 2019. Behind the transformer sits its core steel: grain-oriented electrical steel (GOES) has one US-owned producer at scale, Cleveland-Cliffs at Butler, Pennsylvania.

The shortage is not only transformers. Switchgear averaged 44 weeks in 2025 and cable, reclosers and pad-mount units all lengthened. Every new substation for a data center, fab, gigafactory or truck depot draws on the same factory slots.

Transformer makers

Who builds large power transformers

The main suppliers to the US market and the largest Chinese makers. US plant locations shown where known.

Large power transformer makers: origin, products, plants
CompanyOriginProductsPlants
Hitachi EnergySwitzerland / JapanPower, distribution, HVDCSouth Boston VA, Alamo TN, Varennes QC; Ludvika SE for HVDC
Siemens EnergyGermanyPower, HVDC, tractionNuremberg DE, Weiz AT; Charlotte NC plant announced
GE VernovaUSAPower, HVDC, distribution (via Prolec GE)Pittsfield MA; Prolec GE joint venture in Monterrey MX
SPX Transformer SolutionsUSALarge power transformersWaukesha WI, Goldsboro NC
Virginia TransformerUSAPower transformers to 765 kVRoanoke VA, Rincon GA, Monterrey MX
HD Hyundai ElectricSouth KoreaPower, HVDCUlsan KR, Montgomery AL
Hyosung Heavy IndustriesSouth KoreaPower, extra-high-voltageChangwon KR, Memphis TN
WEGBrazilPower, distribution, dry-typeJaragua do Sul BR, Mexico, US plants
TBEAChinaPower to 1,200 kV UHVXinjiang, Shenyang, Hengyang CN
China XD GroupChinaPower, HVDC, GISXi'an CN

Electrical steel

The steel inside the transformer

Grain-oriented electrical steel is rolled so its grains line up with the magnetic field, cutting core losses. Few mills can make the high-permeability grades large transformers need.

Grain-oriented electrical steel producers: location, approximate capacity (kt/yr), notes
ProducerMillskt/yrNotes
Cleveland-CliffsButler PA, USA~250Only US-owned GOES producer at scale
Nippon SteelHikari and Yawata, Japan~700Highest-grade HiB; also motor steel
JFE SteelChiba and Fukuyama, Japan~300HiB and CGO
POSCOPohang, South Korea~400HiB and CGO; motor steel
thyssenkrupp Electrical SteelGelsenkirchen, Germany~250Main EU producer
voestalpineLinz, Austria~150Transformer and motor grades
Tata SteelIJmuiden, Netherlands~200CGO grades
Baowu (incl. WISCO)Baoshan and Wuhan, China~900Mostly serves China's own grid

Grid topics

Grid pages

Grid topic pages
PageCovers
T&D UpgradesTransmission and distribution expansion and reconductoring
HVDC and MVDCDC corridors and DC distribution
Solid-State TransformersPower-electronic transformers at grid nodes
Grid Edge and DERRooftop solar, storage, EVs and V2G
Grid Controls and AutomationSCADA, ADMS, DERMS, metering
Grid Resilience and HardeningPhysical and weather hardening
Grid CybersecurityConverged IT and OT security
AI and Digital TwinsSimulation and predictive maintenance

Sources

Sources and scope

Scope
US grid equipment constraint: transformers, switchgear and electrical steel
Sources
Wood Mackenzie, Untangling the US transformer supply chain crisis (August 2025) and Q2 2025 lead-time survey; company plant disclosures
Updated