Finding
Fault automation is the cheapest resilience gain and undergrounding the most expensive, so utilities spend by corridor risk rather than across the system
Winter Storm Uri left more than 4.5 million Texas homes and businesses without power in February 2021; Hurricane Beryl cut power to about 2.26 million CenterPoint customers in Houston in July 2024. Utility equipment has been linked to the Camp Fire (2018, PG&E), the Lahaina fire (2023, Hawaiian Electric) and the Smokehouse Creek fire (2024, Xcel), the largest in Texas history.
The response splits by hazard. Florida's 2019 storm protection plan law drives pole replacement and undergrounding; California utilities file wildfire mitigation plans built on covered conductor, fast-trip settings and public safety power shutoffs, and Victoria in Australia mandated rapid earth fault current limiters (REFCL) after Black Saturday. ERCOT added winterization rules after Uri. China's State Grid and China Southern Grid rebuilt ice-loading standards after the 2008 southern ice storm.
Restoration is the other half. Automated fault location, isolation and service restoration (FLISR) shrinks outages from hours to minutes for a fraction of the cost of burying lines, and microgrids with batteries keep critical sites running when the feeder is down.
Measures
Hardening measures
Ranked from broadest adoption to most selective.
| Measure | Technology | Function | Where it leads | Outlook |
|---|---|---|---|---|
| Sectionalizing and automation (FLISR) | Automated reclosers, switches, ADMS | Isolates faults and reroutes power | Most large US utilities | Widespread; low cost, high SAIDI/SAIFI gain |
| Wildfire mitigation | Covered conductor, fast-trip relays, REFCL, PSPS, cameras | Cuts ignition risk | California, Texas Panhandle, Mountain West, Australia, Mediterranean | Rapid growth; mandatory in California and Victoria |
| Storm hardening | Steel and concrete poles, guying, flood walls | Survives hurricane wind and surge | Florida, Gulf Coast, Carolinas | Rate-approved programs in the Southeast |
| Black start and microgrids | Onsite generation, BESS, microgrid controllers | Restores or holds load without the grid | Hospitals, defense, data centers | Steady growth for critical loads |
| Undergrounding | Buried cable, duct banks | Removes wind, ice and fire exposure | Urban cores, high-fire corridors (PG&E) | Targeted, not universal, due to cost |
Events
Outages and fires that set the agenda
| Event | Year | Impact | What changed |
|---|---|---|---|
| Camp Fire, California | 2018 | 85 deaths; PG&E transmission line | Wildfire mitigation plans, PSPS, undergrounding pledge |
| Winter Storm Uri, Texas | 2021 | 4.5M+ homes and businesses without power | ERCOT winterization rules, market reforms |
| Moore County substations, North Carolina | 2022 | Gunfire disabled two substations; about 45,000 customers out for days | Physical security reviews, spare transformer programs |
| Lahaina fire, Maui | 2023 | 102 deaths; Hawaiian Electric lines | Utility shutoff programs in Hawaii |
| Smokehouse Creek fire, Texas | 2024 | Largest wildfire in Texas history; Xcel equipment involved | Texas utility wildfire plans |
| Hurricane Beryl, Houston | 2024 | About 2.26M CenterPoint customers out | CenterPoint resiliency plan: poles, undergrounding, automation |
Bottlenecks
What slows hardening
| Bottleneck | Constraint | Impact |
|---|---|---|
| Undergrounding cost | $2-10 million per mile in urban areas | Limits it to the highest-risk corridors |
| Equipment lead times | Transformers, conductors, switchgear | Delays rebuilds and spares |
| Workforce | Lineworkers and trenching crews | Caps annual miles hardened |
| Cost recovery | Multi-billion-dollar plans need rate approval | Affordability pushback from regulators |
| Integration | FLISR, OMS and ADMS not always interoperable | Slows automated restoration |
Sources
Sources and scope
- Scope
- Grid Resilience and Hardening
- Sources
- ERCOT and PUCT reports on Winter Storm Uri; CenterPoint; CAL FIRE; Maui Police Department; Florida PSC; NERC
- Updated
- October 2026