Grid Equipment Supply Chain

steel · parts · transformers · cable

Every tier from electrical steel to HVDC cable has a handful of suppliers and a multi-year backlog. New US transformer plants open from 2027, after the shortage peaks.

Grid equipment supply chain from electrical steel to substation. Each tier has few suppliers: about 10 mills make grain-oriented electrical steel, one of them US-owned at scale; the top three tap-changer makers hold about 90%; large power transformers take about 128 weeks and generator step-up units 144; three European cable makers hold about two-thirds of the HVDC cable market with slots booked to about 2030. Wood Mackenzie projects the US power transformer shortfall falling from 30% in 2025 to about 5% in 2030, and for step-up units from 47% to 14%, as new plants open from 2027. FEW SUPPLIERS AT EVERY TIER STEELGOES ~10 mills1 US-owned PARTSTap changers top 3 ~90%bushings: few EQUIPMENTTransformers 128 wk80% imported CABLEHVDC cable 3 makers ~2/3booked ~2030 US SUPPLY SHORTFALL, WOOD MACKENZIE 0% 25% 50% 2025 2027 2030 Step-up (GSU) 47%14% Power transformers 30%5% New US plants open
Transformer lead
128 wk
Tap changers, top 3
~90%
US GOES makers
1
Shortfall 2030
~5%
Hub
Supply Chain

Finding

A few factories at each tier, and the new ones arrive after the peak

Grid equipment runs through a short chain with few suppliers at every step. About 10 mills worldwide make grain-oriented electrical steel (GOES) for transformer cores, and Cleveland-Cliffs is the only US-owned one at scale. Three makers - Maschinenfabrik Reinhausen, Huaming and Hitachi Energy - hold about 90% of on-load tap changers. Large power transformers take about 128 weeks. Prysmian, Nexans and NKT hold about two-thirds of the HVDC cable market with factory slots booked toward 2030.

The response is a wave of factory investment, but it lands late. Siemens Energy's Charlotte, North Carolina plant starts large power transformers in early 2027; Hitachi Energy's Alamo, Tennessee expansion, set to become North America's largest bushing plant, is due mid-2027. Wood Mackenzie projects the US power transformer shortfall falling from 30% in 2025 to about 5% by 2030, and for generator step-up units from 47% to 14%. Through 2027 the queue is set by factories that already exist, most of them abroad.

The chain overlaps with electrification everywhere else. Copper goes into windings and cable, the same steel mills make motor laminations for EVs, and data centers, gigafactories, solar farms and truck depots all compete for the same transformer slots.

The chain

Nine inputs from steel to substation

Rows are colored by the Bottleneck Atlas states: binding, tight or concentrated.

Grid equipment supply chain: input, use, main suppliers, constraint
InputUsed forMain suppliersConstraint
Electrical steel (GOES)Transformer coresNippon Steel, Baowu, POSCO, JFE, thyssenkrupp, Cleveland-CliffsAbout 10 mills; China's output mostly stays in China
Copper and aluminum conductorWindings, busbars, cableCodelco, Freeport, Southern Copper; refining 47% in ChinaUS copper tariff raises winding cost
Insulation and oilPressboard, paper, mineral and ester oilsWeidmann, Nynas, Cargill (ester)Few pressboard makers
On-load tap changersVoltage regulation in power transformersMaschinenfabrik Reinhausen, Huaming, Hitachi EnergyTop three about 90%
BushingsHV connections through the tank wallHitachi Energy, MR (via subsidiaries), Trench, Siemens EnergyHitachi Alamo TN expansion due 2027
Large power and step-up transformersSubstations, generator connections, data centersHitachi Energy, Siemens Energy, GE Vernova, HD Hyundai, Hyosung, SPX, Virginia Transformer, TBEA128-144 weeks; 80% of US supply imported
Distribution transformersPole and pad-mount units at the edgeEaton, Howard Industries, ERMCO, Prolec GE, Hitachi EnergyAbout 30 weeks; half imported
Switchgear and breakersProtection and switching in substationsHitachi Energy, Siemens Energy, Schneider, Eaton, ABB, Mitsubishi ElectricAbout 44 weeks; SF6 being phased out in the EU
HV and HVDC cableInterconnectors, offshore wind, undergroundingPrysmian, Nexans, NKT, LS Cable, Sumitomo ElectricThree Europeans about two-thirds of HVDC; booked toward 2030

New capacity

Factories under way

Announced transformer and component investments serving North America.

Announced grid equipment factory investments
CompanySiteInvestmentWhat and when
Hitachi EnergyUS and global$1.5B transformers by 2027, plus $250M for componentsSouth Boston VA, Jefferson City MO, Mississippi, Varennes QC
Hitachi EnergyAlamo, Tennessee$106MLargest bushing plant in North America, mid-2027
Siemens EnergyCharlotte, North CarolinaNew large power transformer lineProduction from early 2027
GE VernovaUnited StatesAbout $600M across US plantsTransformers and grid equipment
HD Hyundai ElectricMontgomery, Alabama and Ulsan$274MAbout 30% more output
Hyosung Heavy IndustriesMemphis, Tennessee$157MExpansion of its 765 kV-capable plant
Pennsylvania TransformerRaeford, North Carolina$102MNew power transformer plant, broke ground December 2025

Makers

Transformer makers and their US plants

Conventional power and distribution transformer makers; solid-state transformer makers are on the Solid-State Transformers page. Status reflects US capacity plans.

Power and distribution transformer makers
CompanyHQProductsUS plantsStatus
Hitachi EnergySwitzerlandPower transformers to 1,200 kV, HVDC converter transformers, distribution transformers, bushingsSouth Boston, Virginia; Jefferson City, Missouri; Alamo, Tennessee (bushings)operating: Largest transformer maker outside China; $1.5B transformer expansion through 2027
Siemens EnergyGermanyPower transformers, HVDC converter transformers, rail traction transformersCharlotte, North Carolina (large power transformers from 2027)operating
GE VernovaUSPower transformers, grid equipmentThrough Prolec GEoperating: Agreed in 2025 to buy Xignux's half of Prolec GE
Prolec GEMexicoDistribution and power transformers, large power transformers to 765 kVWaukesha, Wisconsin; Goldsboro, North Carolina (former SPX Transformer Solutions, bought 2021); Shreveport, Louisianaoperating: Largest transformer supplier to North America; joint venture of Xignux and GE Vernova
Virginia TransformerUSPower and distribution transformers to 765 kVRoanoke, Virginia; Rincon, Georgia; Pocatello, Idahooperating: Largest US-owned power transformer maker
Pennsylvania Transformer TechnologyUSPower transformersCanonsburg, Pennsylvania; Raeford, North Carolina (new plant)expanding: Raeford plant broke ground December 2025
HD Hyundai ElectricSouth KoreaPower transformers to 765 kV, HVDC transformers, switchgearMontgomery, Alabamaexpanding: About 30% more output from Alabama and Ulsan
Hyosung Heavy IndustriesSouth KoreaPower transformers to 765 kV, switchgearMemphis, Tennesseeexpanding
WEGBrazilPower, distribution and dry-type transformersWashington, Missourioperating
EatonUSDistribution transformers, switchgear; solid-state transformers via Resilient PowerWaukesha, Wisconsin; Jonesville, South Carolinaexpanding
Howard IndustriesUSDistribution transformersLaurel, Mississippioperating
ERMCOUSDistribution transformersDyersburg, Tennesseeoperating
CG Power and Industrial SolutionsIndiaPower and distribution transformers-operating: Murugappa Group company
TBEAChinaPower transformers to 1,100 kV UHV, distribution transformers-operating: China's largest transformer maker; limited access to Western utilities
China XD GroupChinaPower transformers, GIS, HVDC equipment-operating: State-owned; part of China Electrical Equipment Group
Tesla EnergyUSMegablock: Megapack 3 units with integrated medium-voltage transformer and switchgearBrookshire, Texas (Megafactory)ramping: Medium-voltage transformer for its own storage blocks, not utility power transformers

Electrical steel

Grain-oriented electrical steel mills

The mills that make GOES for transformer cores. Japan, Korea and Europe supply the export market; China's large output mostly stays in China.

Grain-oriented electrical steel (GOES) mills
CompanyMillCountryGradesMain customersNotes
Cleveland-CliffsButler WorksUSHiB and conventional GOES; domain-refinedUS transformer makersOnly US producer of GOES; finishing at Zanesville, Ohio
Nippon SteelHikari WorksJapanORIENTCORE HiB and conventionalGlobal transformer makersLargest GOES maker by quality grade; bought U.S. Steel in June 2025 (U.S. Steel makes no GOES)
Nippon SteelYawata Works (Kitakyushu)JapanHiB GOES; NOES for EV motorsJapanese transformer and auto makers-
JFE SteelKurashiki and Chiba (Kurashiki / Chiba)JapanJGSD HiB and conventional; NOESGlobal transformer makersCo-owns JSW JFE Electrical Steel in India
POSCOPohang WorksSouth KoreaHiB and conventional; NOESKorean transformer makers (HD Hyundai Electric, Hyosung), Hyundai Motor Group-
Baowu Steel (Baosteel)Baoshan Works (Shanghai)ChinaHiB and conventional; NOESChinese transformer and EV makersWorld's largest steelmaker; little GOES leaves China
Baowu Steel (WISCO)Wuhan WorksChinaConventional and HiB; NOESChinese transformer makersBaowu subsidiary since 2016
ShougangQian'an WorksChinaHiB and conventional; NOESChinese transformer and EV makersSecond large Chinese GOES producer
thyssenkrupp Electrical SteelGelsenkirchen and Isbergues (Gelsenkirchen / Isbergues)Germany, Francepowercore HiB and conventionalEuropean transformer makers-
StalproduktBochniaPolandConventional GOESEuropean transformer makers-
JSW JFE Electrical SteelNashikIndiaGOESIndian transformer makersFormer thyssenkrupp Electrical Steel India
NLMKVIZ-Steel (Yekaterinburg)RussiaConventional and HiBRussian and Asian buyersExports curbed by sanctions

Sources

Sources and scope

Scope
Grid equipment from electrical steel and conductor to transformers, switchgear and HV cable
Sources
Wood Mackenzie transformer supply chain report and lead-time survey (2025); company announcements; NKT and Prysmian investor reports; OLTC market studies
Updated
October 2026