Battery cells, polysilicon and lithium were the shortages of 2022; China overbuilt all three. What stopped plants and projects in 2025 was what nobody overbuilt: power transformers, rare earth magnets and the precision reducers inside robot joints.

Overbuilt versus binding: battery cells, polysilicon and lithium are in surplus, while power transformers, rare earth magnets and precision reducers are binding constraints. OVERBUILT BATTERY CELLS ~3x capacity vs 2024 demand POLYSILICON ~3x capacity vs 2026 installs LITHIUM -80%+ price since 2023 BINDING POWER TRANSFORMERS 128 wk US lead time; 30% shortfall NDFEB MAGNETS -77% China exports, March to May 2025 REDUCERS Japan humanoid joints wait on them
Binding
4
Tight
3
Concentrated
2
Surplus
4
Not yet at scale
1
Hub
Supply Chain

Ranked by what binds now

Four Bottlenecks Bind Today; Four Former Ones Are in Surplus

Each input is rated by what it is doing to deployments now, not by how concentrated it is. Concentration and shortage are different problems: China refines 94% of battery-grade graphite, but graphite is not short.

State
14 bottlenecks
BottleneckState, 2026EvidenceWhere it bites
Power transformers and electrical steel (GOES)Binding128-week US lead times; 30% US shortfall in 2025; about six GOES makersGrid, charging depots, data centers, gigafactories
Rare earth magnets (NdFeB, dysprosium, terbium)BindingChina export licenses from April 2025; magnet exports down 77% by MayEVs, robots, drones, wind turbines
Strain-wave reducers and actuator modulesBindingJapan-led reducers; Chinese modules at a 60-80% cost leadHumanoids, industrial robots
Grid interconnection and new generationBindingLarge loads wait years for utility serviceCharging depots, data centers, factories
SwitchgearTight44-week US lead timesEvery site with a medium-voltage feed
Mature-node control and analog chipsTight18-24 months to requalify a replacement partEvery vehicle, charger, inverter and robot
CopperTightChina refines 47%; new mines take a decade or moreMotors, transformers, cables, busbars
Battery-grade graphiteConcentrated, not shortChina refines 94%; export permits required since December 2023EVs, grid batteries, robots
Cathode active materialConcentrated, not shortChina makes about 85%EVs, grid batteries
SiC wafersSurplusChinese wafers cut prices by two-thirds; Wolfspeed through Chapter 11EV inverters, chargers, solar, grid batteries
Lithium chemicalsSurplusPrices down more than 80% since 2023; China refines 74%Every lithium-ion cell
Battery cellsSurplusGlobal capacity about 3x demandEVs, grid batteries, robots
Polysilicon, wafers and solar cellsSurplusCapacity about 3x 2026 installations; China holds 80%+ of each stageSolar
Tactile sensor arraysNot yet made at scaleNo supplier at production scaleHumanoid hands

Overbuilt

Overbuilding Turned the Battery and Solar Bottlenecks Into Surpluses

In 2022, cells, lithium, polysilicon and SiC were the headline shortages. By 2025 each had more capacity than demand, most of it built in China.

Cell capacity passed 3 TWh, about three times demand. Polysilicon capacity reached about 2,034 GW against 638 GW of 2026 installations. Lithium prices fell more than 80% after an eightfold rise, and Chinese SiC wafers sold for a third of the old price. Surplus did not end concentration: China still controls most of each stage, and it has used export permits on graphite since December 2023. See the Battery and Solar PV supply chains.

Binding

What Binds Takes Years to Build and Nobody Overbuilt

Transformers, rare earth magnets and precision reducers have long lead times, specialized know-how and few producers, and none of them got the capacity race batteries did.

  • Transformers: grain-oriented electrical steel comes from about six makers, and US power transformer lead times averaged 128 weeks in 2025, with imports supplying about 80%. See Charging and Depot.
  • Magnets: China's April 2025 export licenses cut its magnet exports 77% in two months and stopped Ford's Explorer line in Chicago for a week. See Motor and Drivetrain.
  • Reducers: strain-wave reducers come mainly from Harmonic Drive Systems and Nabtesco; a humanoid needs one in most of its 28 or more joints. See Robot.

Recycling

Recycling Relieves Metals, Not Steel, Wafers or Chips

Recycling adds supply only where the constrained input is a recoverable material that can be refined back to specification.

Recycling leverage by bottleneck
BottleneckRecycling leverageWhy
Lithium, nickel, cobaltHighBlack mass refines back to battery-grade salts
CopperHighAlready one of the most recycled metals
Rare earth magnetsMediumMagnet-to-magnet recycling works but volumes are small
GraphiteMediumRecoverable, harder to return to anode grade
Electrical steel, SiC wafers, control chipsLowProcess-limited or qualification-limited, not material-limited

Sources

Sources and scope

Dataset
Electrification bottlenecks rated by state in 2026
States
Binding: deployments are waiting on it now. Tight: long lead times without stopping work. Concentrated, not short: one country dominates but supply is ample. Surplus: capacity well above demand
Sources
Figures cited on each linked chain page: IEA, Wood Mackenzie, Adamas Intelligence, TrendForce, Intertek CEA