Energy Throughput per Acre

MWh per acre · grid cap · stall density · dwell

A depot's useful output is the energy it puts into vehicles each day, divided by its land. Below the grid cap, layout and scheduling set the number; at the cap, only storage or a bigger feed raises it.

Illustrative ElectronsX model of energy delivered per acre per day, log scale: a grid cap of 10 MW on a 5-acre site allows 48 MWh per acre per day; Truck depot, MCS stalls about 40 MWh; Robotaxi depot, DC stalls about 29 MWh; Truck depot, overnight CCS about 15 MWh; Car fleet lot, Level 2 about 6.7 MWh; Humanoid dock network about 0.6 MWh; Drone dock field about 0.12 MWh. The metric is dock-metered energy per day divided by developed acres; the ceiling is grid import plus solar plus battery discharge over 24 hours, divided by acres. MWh DELIVERED PER ACRE PER DAY, ILLUSTRATIVE MODEL (LOG SCALE) Cap: 10 MW, 5 acres48 Truck depot, MCS~40 Robotaxi depot, DC~29 Truck depot, CCS~15 Car fleet, Level 2~6.7 Humanoid docks~0.60 Drone docks~0.12 0.1 1 10 100 Dock-metered MWh per day ÷ developed acres Ceiling: (grid import + solar + BESS discharge) × 24 h ÷ acres
Unit
MWh/acre/day
Truck MCS model
~40
Robotaxi model
~29
10 MW, 5 acres
48 cap
Hub
Charging

Finding

A well-run truck or robotaxi depot delivers on the order of 30-40 MWh per acre per day, which is about what a 10 MW feed can supply to five acres, so dense depots hit the grid cap before they run out of land

In the ElectronsX model, eight MCS stalls per acre averaging 600 kW at 35% occupancy deliver about 40 MWh per acre per day; 40 robotaxi DC stalls averaging 60 kW at 50% occupancy deliver about 29. A 10 MW connection spread over five acres caps delivery at 48. Humanoid and drone docks deliver one to two orders of magnitude less energy per acre, so for them land and approach paths, not power, are the limit.

The metric is simple: energy metered at the dock or charger output each day, divided by developed site acres. Metering at the dock matters. The original form of this metric multiplied delivered energy by battery round-trip efficiency, which double-counts losses: energy measured where it enters the vehicle already excludes what the BESS and converters lost. Those losses belong in a separate site-efficiency ratio (dock energy divided by grid import plus on-site generation), typically 85-90% for energy that cycles through lithium-ion storage and about 95% for direct charging.

Storage raises the number only when the grid is the limit. A BESS charged during off-peak hours lets a site deliver more energy at the fleet peak than its feed could supply in real time, so it acts as land productivity infrastructure, not only backup. Packaging matters too: Tesla's Megablock combines four Megapack 3 units with a medium-voltage transformer and switchgear on one skid, cutting the land that electrical gear takes from charging bays; Megapack 3 and Megablock are built at Brookshire, Texas. CATL TENER, BYD MC Cube and Sungrow PowerTitan compete for the same depot buffers.

Model

Illustrative throughput by asset class

ElectronsX model, not measured site data. Change any input and the result scales linearly.

Energy throughput per acre, illustrative model
SiteCharging points per acreAverage kW while occupiedOccupancy over 24 hMWh per acre per day
Truck depot, MCS stalls860035%~40
Robotaxi depot, DC stalls406050%~29
Truck depot, overnight CCS820040%~15
Car fleet lot, Level 2120733%~6.7
Humanoid dock network100125%~0.60
Drone dock field200.830%~0.12
Grid cap: 10 MW feed on 5 acres---48

Variables

What sets throughput per acre

Energy throughput variables
VariableWhat it setsLever
Grid interconnectionUpper bound on sustained deliveryLarger service; ERCOT or utility large-load process; phased upgrades
BESS energy and powerHow much peak delivery exceeds the feedSize MWh to the peak window and MW to the stall count
Charging point densityHow many assets replenish at oncePull-through truck stalls; angled car stalls; wall and floor robot docks
Average delivered powerEnergy per occupied hourCharger rating, battery taper, thermal limits
Dwell and occupancyShare of the day each point delivers energyDispatch software; idle fees; robotic plug-in
Queue and circulationLand spent waiting, aligning and turningSeparate queue lanes; drive-through layouts; wireless pads
Conversion lossesGap between grid import and dock energyDirect DC coupling of BESS and solar; efficient SiC power stages

Work metrics

Linking energy to work by site type

Energy per acre is the physical base; the business metric is the work it enables.

Energy and work metrics by site type
Site typeEnergy metricWork metric
Robotaxi depotMWh per acre per dayPassenger-miles or trips enabled per acre per day
Autonomous truck depotMWh per acre per day; MCS stall-hoursFreight ton-miles enabled per acre per day
Energy autonomy yardMWh per acre per day across all classesTrailer moves, picks and missions per acre per day
Humanoid and AMR fleetkWh per building floor areaTask-hours enabled per day
Drone dock networkkWh per dock per dayMissions or inspections completed per day
Port or rail terminalMWh per acre per dayContainer or trailer moves per acre per day

Sources

Sources and scope

Scope
Energy Throughput per Acre
Sources
ElectronsX throughput model (illustrative); Tesla (Megablock, Megapack 3); BESS round-trip efficiency from supplier data
Updated
October 2026